NEW QUESTION # 453
A project's key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed? (Choose two.)
- A. KPI
- B. WBS
- C. Project schedule
- D. Cost performance parameter
- E. Corrective action plan
Answer: B,C
Explanation:
References:
Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 133
https://books.google.co.za/books?id=evR0gPFBHJ4C&pg=PA128&lpg=PA128&dq=complete+a+project+sooner+-+update+WBS&source=bl&ots=O650UKpUEK&sig=mlexbBmFJKkAuXuftqO2YjLLOgo&hl=en&sa=X&ved=0ahUKEwi8uJXIj_DXAhUKuRQKHW3fDKAQ6AEIMTAC#v=onepage&q=complete%20a%20project%20sooner%20-%20update%20WBS&f=false
NEW QUESTION # 454
A project manager is not receiving cooperation from a department that is vital to the success of a project. Because of this, the project cannot move forward. Which of the following is the BEST place the project manager should go to get help with this issue?
- A. Project team
- B. Project sponsors
- C. Project management office
- D. Project stakeholders
Answer: C
NEW QUESTION # 455
A key stakeholder asked several members of the project team to make project changes without submitting them for approval. Because the stakeholder is related to the Chief Executive Officer (CEO), the team members are reluctant to deny these requests. Which of the following should the project manager do FIRST to control this situation?
- A. Request additional resources from the project team to complete the change requests from the key stakeholder
- B. Ask the project sponsor for more funding to anticipate the change requests from the key stakeholder
- C. Have the team members deny all change requests from this stakeholder
- D. Contact the key stakeholder to encourage the submission of written change requests
Answer: D
NEW QUESTION # 456
A project manager is collecting work package information from the project team for the first time.
Which of the following elements should the project manager have at the end of the meeting?
- A. Task start, finish, and estimate cost
- B. Task assignments, quality requirements, and project governance sign-off
- C. Task leveling, baseline, and critical path
- D. Task name, duration, and dependencies
Answer: B
NEW QUESTION # 457
Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Select two.)
- A. Earned value
- B. Cost variance
- C. Acceptable variance
- D. Schedule variance
- E. Planned value
Answer: A,B
NEW QUESTION # 458
A project has a ВАС of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget. Which of the following should the project manager do NEXT?
- A. Obtain approval from the CCB.
- B. Evaluate the impact and justify adding new work to the project.
- C. Add the required work to complete the project behind $892,500.
- D. Request a budget increase of $170,000.
Answer: A
Explanation:
Explanation/Reference:
NEW QUESTION # 459
A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review and approval. The following sections are currently documented:
* Project description
* Draft project timeline and schedule
* Rough milestones
* Draft project budget
* Draft resources required
* High-level risk review
Which of the following sections should be included in this document?
- A. Full risk assessment results
- B. Business information
- C. Full resource requirements
- D. Draft work breakdown structure
Answer: D
NEW QUESTION # 460
Because a feature was not meeting documented requirements, a project milestone was not achieved as scheduled. Which of the following activities should the project manager perform NEXT?
- A. Calculate the schedule variance and update the project status.
- B. Update the project scope and obtain sponsor approval.
- C. Review quality control processes and make the necessary improvements.
- D. Schedule a meeting with stakeholders and update the project objectives.
Answer: A
NEW QUESTION # 461
The project manager has noticed a vendor is not performing in accordance with the SLA.
Which of the following items should the project manager use to highlight the vendor's areas of poor performance?
- A. WBS
- B. Balanced score card
- C. Post-project evaluation
- D. PERT
Answer: B
NEW QUESTION # 462
Which of the following documents should be used to provide high-level reporting to key stakeholders?
- A. Project charter
- B. Statement of work
- C. Dashboard
- D. Communication plan
Answer: C
Explanation:
Explanation/Reference:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 325
NEW QUESTION # 463
Two parties are beginning conversations regarding the purchase of professional services. Which of the following should be in place FIRST?
- A. RFP
- B. NDA
- C. LOI
- D. SOW
Answer: A
NEW QUESTION # 464
The executive sponsor asks a project manager to summarize the following for a project:
1. Final capital expenditures.
2. Anticipated cost of new employee resources to support the solution.
3. Maintenance estimates.
Which of the following information should the project manager provide?
- A. Cost variance report
- B. Burn rate
- C. Cost baseline
- D. Total project cost
Answer: C
NEW QUESTION # 465
A stakeholder informs a project manager that a weekly status report has not been delivered via email, but the monthly status reports were received. Which of the following should the project manager do NEXT?
- A. Add email to the distribution list for the weekly status report
- B. Consult the communications plan and act accordingly
- C. Remove email from the distribution list for the monthly status report
- D. Immediately send the current weekly status report
Answer: A
NEW QUESTION # 466
Which of the following statements are correct regarding project management? (Select two.)
- A. A program has a defined start and finish.
- B. A project portfolio will be managed under program management.
- C. An organization's portfolio is a temporary and unique endeavor.
- D. A project can be part of an organization's program management.
- E. An organization's portfolio will include programs.
Answer: A,E
NEW QUESTION # 467
Many Question: 01s have arisen regarding a newly identified project. Project team members are anxious to know who will be part of the team and what the project will deliver. Which of the following would be the BEST way to provide this information?
- A. CCB meeting
- B. Status report
- C. Kickoff meeting
- D. Company-wide email
Answer: C
NEW QUESTION # 468
Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?
- A. Daily standup meeting
- B. Review meeting
- C. Sprint planning meeting
- D. SCRUM retrospective meeting
Answer: C
Explanation:
Explanation/Reference:
References: https://www.atlassian.com/agile/ceremonies
NEW QUESTION # 469
A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints.
Which of the following documents should the project manager use to obtain this information?
- A. Balanced scorecard
- B. Issue log
- C. Status report
- D. Project schedule
Answer: C
NEW QUESTION # 470
A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low and high bids must be rejected to determine the selected vendor.
Which of the following terms describe this requirement?
- A. Business acquisition
- B. Internal reorganization
- C. Business process change
- D. Outsourcing
Answer: D
Explanation:
Explanation
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 297
NEW QUESTION # 471
A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked.
Which of the following documents should the project team reference to fast-track the project? (Choose two.)
- A. Configuration management plan
- B. Project plan
- C. Scope management plan
- D. Project schedule
- E. Network diagram
Answer: D,E
Explanation:
Explanation
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 171
NEW QUESTION # 472
A project sponsor and Chief Information Officer (CIO) disagree about how to release the final deliverables to the market. The sponsor wants to do a massive product release, while the CIO wants to be extremely cautious and add more time for testing and defect resolution. The project manager works with both parties and determines the best solution is to roll the product out in a pilot release to see how it tests, and then use customer feedback to determine next steps.
Which of the following conflict resolution techniques is the project manager using?
- A. Avoiding
- B. Compromising
- C. Negotiating
- D. Forcing
Answer: C
Explanation:
Explanation/Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 200
NEW QUESTION # 473
Gas prices were included in the cost baseline for a transportation and hauling project. Although the estimates used to create the baseline were based on historical data, which of the following should the project manager consider as a root cause for potential issues with cost overruns?
- A. Environment
- B. Budget
- C. Requirements
- D. Lessons learned
Answer: B
NEW QUESTION # 474
During the planning phase, a scheduler uses a WBS as a reference to create a list of activities. The next step of the process is to provide a sequence for all the activities. With which of the following deliverables is the scheduler working?
- A. Project timeline
- B. WBS dictionary
- C. Network diagram
- D. Gantt chart
Answer: D