ISTQB CT-TAE Exam is an advanced-level certification that requires candidates to have a good understanding of software testing principles and practices, as well as experience in test automation. CT-TAE exam is based on the ISTQB Test Automation Syllabus, which covers the core concepts and techniques of test automation. CT-TAE exam is divided into two parts: a multiple-choice section and a practical section. The multiple-choice section tests the candidate's knowledge of test automation concepts and techniques, while the practical section assesses the candidate's ability to design and implement test automation solutions. Passing the ISTQB CT-TAE Exam demonstrates that a candidate has the skills and knowledge required to design, develop, and manage effective test automation solutions.
NEW QUESTION # 42
Consider the following layers of the gTAA structure:
a. Test generation layer
b. Test definition layer
c. Test execution layer
d. Test execution layer
Consider the following capabilities associated with these layers.
Acquire all the necessary resources before each test and release all after run, in order to avoid interdependences between test Allow the automated test scripts on an abstract level to interact with components, configurations and interfaces of the SUT.
Design test directives that allow configuring the algorithms used to automatically produce the test cases a given model of the SUT.
Allow the definition and implementation of test cases and data by means of templates and/or guidelines.
Which of the following BEST matches each layer with the appropriate capability?
- A. a-4, b-3, c-2, d-1
- B. a-3, b-4, c-1, d-2
- C. a-4, b-3, c-1, d-2
- D. a-3, b-4, c-2, d-1
Answer: A
NEW QUESTION # 43
You have been asked to develop test automation for a legacy system that is going to go through a series of infrastructure migrations. The scripts will be used to verify basic functionality during these infrastructure changes Your Test Analysts have some programming skills and need a solution that is simple and fast.
Maintainability of the scripts is not a consideration because no changes to the software are anticipated.
Which of the following is the BEST scripting approach in this situation?
- A. Model-Based scripting
- B. Structured scripting
- C. Linear scripting
- D. Capture-replay scripting
Answer: D
NEW QUESTION # 44
Which of the following statements about the reuse of TAS artefacts is TRUE?
- A. To enable reuse of TAS artefacts, a good design for reuse is built into the TAA and to further action are needed during the TAS lifecycle
- B. Reusable TAS artefacts can include components (or parts of components) associated with different layers of the TAA
- C. Communications maintenance and improvements for reusing TAS artefacts are modify addressed during the design of the TAA
- D. Reusable TAS artifacts associated with the definition layer of the TAA include the adaptors to the SUT components and/or interfaces
Answer: A
NEW QUESTION # 45
Your project is transitioning from manual to automated testing. You have decided to implement a pilot project so that lessons learned can inform future time estimates and schedules.
Which two of the following represent the types of test cases that are MOST suited to a test automation pilot project?
a) High added value test cases that require little effort to automate.
b) Test that are run infrequently as these will be simpler to automate
c) Reliability test cases that can show added value soon
d) Technically challenging test cases to provide the best validation of manual test conversion e) Tests that are least Important to the business as these are safer to trial
- A. a and b
- B. a and c
- C. b and d
- D. c and e
Answer: B
NEW QUESTION # 46
A web application was released into production one year ago, it has regular release which follow a V-model lifecycle and testing is well-established and fully integration into the development lifecycle. You have been asked to implement a TAS for the regression test suite. The regression tests have been developed via the GUI and are expected to be run at least four times a month, for each planned release, for the whole operation solution life of the system (six years). Each screen of the GUI uses several third-party controls which are not compatible with the existing automation solutions. The environment for the automation will be stable, fully controllable and separated from other environments (development, staging, production).
What could be the MOST problematic for this TAS?
- A. Sustainability of the automated environment
- B. Frequency of use
- C. Complexity to automate
- D. Maturity of the test process
Answer: C
Explanation:
The most significant challenge in implementing a Test Automation System (TAS) for the given scenario is the complexity to automate, primarily due to the use of several third-party controls that are not compatible with existing automation solutions. This incompatibility introduces a high level of complexity because it may require custom solutions or workarounds to automate these controls. Additionally, the need to run the regression tests at least four times a month for each planned release over the system's entire operational life further compounds the complexity, as it necessitates a robust and maintainable automation framework that can handle frequent executions without significant maintenance overhead.
References = The answer is derived from the ISTQB Test Automation Engineer syllabus, which emphasizes the importance of selecting appropriate tools and designing a maintainable and scalable automation framework that can handle the complexities of the application under test12. The syllabus also discusses the challenges and considerations when automating tests that involve third-party controls and components12.
NEW QUESTION # 47
You have executed an automated test suite for a product that was released into production. Although all the tests passed, there was a major failure in production in an area that was covered well by your automated tests.
You have run the automated tests again and one of the tests is now failing and this is directly related to the production defect that was raised. You decide to run the automated test suite again on the same version of the SUT and the test now passes.
What SHOULD you do now to verify the validity of the automated tests?
- A. Remove the intermittently failing test from the test suite and investigate the reason why the test sometimes passes and sometimes fails.
- B. Reference:
https://www.researchgate.net/publication/341396240_Intermittently_Failing_Tests_in_the_Embedded_Sys - C. Run the automated test suite again and if the test now passes - do nothing
- D. Check that the production defect that was reported was an actual defect
Answer: A
Explanation:
When faced with an intermittently failing test, it is essential to remove it from the test suite to prevent it from affecting the overall test results and reliability. The next step is to conduct a thorough investigation to understand why the test is producing inconsistent results. This could involve examining the test environment, the test data, the timing of the test execution, and any potential race conditions or dependencies that could cause the test to behave differently from one run to another. Understanding and resolving the root cause of the intermittent failure is crucial to ensure the stability and accuracy of the automated test suite.
References = The approach to handling intermittently failing tests is discussed in various ISTQB Test Automation Engineer documents, which emphasize the importance of maintaining the integrity of the test suite and ensuring consistent and reliable test results123.
NEW QUESTION # 48
As a TAE you are evaluating a functional test automation tool that will be for several projects within your organization. The projects require that tool to work effectively and efficiently with SUT's in distributed environments. The test automated tool also needs to interface with other existing test tools (test management tool and defect tracking tool.) The existing test tools subject to planned updates and their interface to the test automated tool may not work property after these updates.
Which of the following are the two LEAST important concerns related to the evaluation of the test automation in this scenario?
Is the test automation tool able to launch processors and execute test cases on multiple machines in different environments?
Does the test automation tool support a licensing scheme that allows accessing different sets?
Does the test automation tool have a large feature set, but only part of the features will be sets?
Do the release notes for the planned updates on existing specify the impacts on their interfaces to other tools?
Does the test automation tool need to install specific libraries that could impact the SUT?
- A. A and C
- B. A and E
- C. B and E
- D. C and D
Answer: C
NEW QUESTION # 49
Assume that you are the TAE responsible for the correct functioning of a TAS, deployed in a test environment that consists of a few machines running the same version of the operating system. The TAS has been working and stable since its deployment, it has been used to run an automated test suite consisting of many similar automated test. The infrastructure team is planning to update the operating system on these machines by installing a new the service pack for security reasons. Since the vendor of the operating system assurance full backward compatibility, the infrastructure team assurance that there will be no impacts on the functioning of the TAS.
What is the BEST approach to confirm the correct functioning of the TAS in this scenario?
- A. Do not run any tests because you can immediately confirm the correct functioning of the automated test suite
- B. Verify the behavior of the automated tests by running a small tests, then gradually run the remaining tests to confirm the correct functioning of the whole automated test suite.
- C. Verify the behavior of the whole automated test suite by running all the automated tests
- D. Make sure that the infrastructure team has completed installing the service pack on the machines where SUT is running, then run the whole automated test suite to verify its behavior
Answer: B
Explanation:
The best approach to ensure the correct functioning of the Test Automation System (TAS) after an operating system update is to start with a small, representative set of automated tests. This allows for the identification of any issues caused by the update with minimal impact. Once the smaller set of tests is confirmed to be working as expected, the remaining tests can be run to ensure the entire suite is functioning correctly. This phased approach helps in isolating problems and ensures that the TAS remains stable and reliable throughout the process.
References = The ISTQB Test Automation Engineer syllabus discusses the importance of verifying the behavior of the TAS in various scenarios, including after updates to the operating system1. It also emphasizes the need for a systematic approach to testing and the potential impact of environmental changes on the TAS12. The syllabus provides guidance on how to manage and maintain the TAS, ensuring its effectiveness and reliability1.
NEW QUESTION # 50
Which of the following is considered a disadvantage of test automation?
- A. Tests are more likely to have operator errors.
- B. Automated exploratory testing is difficult to implement
- C. Slower feedback on the quality of the system.
- D. Test automation can be a distraction from the objective of finding bugs
Answer: B
Explanation:
Automated exploratory testing is challenging because it relies heavily on human intuition, experience, and real-time decision-making, which are difficult to replicate with automated systems. While test automation offers many advantages, such as repeatability and efficiency, it lacks the creativity and adaptability of a human tester exploring the software without predefined scripts or scenarios. This limitation can be significant, especially when the goal is to discover new and unexpected issues within the system under test.
References = The ISTQB CT-TAE materials discuss the objectives, advantages, disadvantages, and limitations of test automation, acknowledging that while automation can significantly enhance testing efficiency, certain aspects like exploratory testing are better suited for manual execution12.
NEW QUESTION # 51
Which of the following is an important success factor for any significant automation project?
- A. The TAA must be designed for testability.
- B. The SUT is self-documenting
- C. The SUT must be designed for testability
- D. The TAA is self-documenting
Answer: C
NEW QUESTION # 52
Designing the System Under Test (SUT) for testability is important for a good test automation approach and can also benefit manual test execution.
Which of the following is NOT a consideration when designing for testability?
- A. Control: the SUT needs to provide interfaces that can be used to perform actions on SUT.
- B. Clearly defined architecture: The SUT Architecture needs to provide clear and understandable interfaces giving control and visibility on all test levels.
- C. Observability: The SUT needs to provide interface that give insight into the system.
- D. Re-useability: The code written for the SUT must be re-useable for other similar system.
Answer: D
NEW QUESTION # 53
A regression test suite consist of 500 test cases which are all executed manually. The business case for a pilot project is based on the adoption of test automation using a commercial tool that will reduce the execution time by a factor of 90% for 100% of the tests in the regression test suite. The pilot project lasted one month ( as planned) and you are currently its results. At the end of the pilot project, 40% of the regression tests have been automated and their execution time has been reduce by 60%.
Which of the following statements is TRUE in this scenario?
- A. The target defined for the business case seems difficult to hit - it should be realistic
- B. The target defined for the business case is too accurate -it should not be measureable
- C. The project selected for the pilot is too critical -if should not be too critical or too trivial
- D. The duration of the pilot project was too short -it should last unit the success factors are achieved
Answer: A
Explanation:
The business case for the pilot project set a very ambitious target: reducing the execution time by 90% for all tests in the regression suite. However, at the end of the pilot, only 40% of the tests were automated with a 60% reduction in execution time. This indicates that the initial target may have been unrealistic within the given timeframe and resources. It's important for business cases to set achievable goals to ensure that the project can meet its objectives and provide a clear return on investment. Setting realistic targets also helps maintain stakeholder confidence and support for the project. References = The ISTQB Test Automation Engineer syllabus and related materials discuss the importance of realistic planning and setting achievable targets in the context of test automation projects. These resources emphasize that while test automation can significantly improve efficiency, the extent and speed of these improvements must be realistically assessed based on the specific context of the project12345.
NEW QUESTION # 54
Consider a TAS that exclusively uses the APIs of a SUT. To make this work, significant changes have been required to the SUT by adding a set of dedicated test interfaces to the APIs. All the automated tests will use these test interfaces when interacting with the SUT. Assume that you are currently verifying the correctness of the automated test environment and test tool setup.
Which of the following would you expect to be the MOST specific risk associated with this scenario?
- A. The connectivity from the TAS to the dedicated test interfaces will not work
- B. False alarms, that are unlikely to occur in the real world, will be observed during testing
- C. The automated test cases will not contain the expected result
- D. The process of configuring the TAS will be error-phone due to manual intervention
Answer: B
NEW QUESTION # 55
You identified a suitable project to pilot an automation tool and planned and conduced a pilot. The pilot has been successful and tool Is being deployed within your organization, with a plan to increase tool use by the one project at a time. During this rollout some test processes will be changed slightly to gain additional benefits from using the tool.
In the pilot project, a small set of manual tests were automated for the first time. You are currently monitoring the test automation efficiency and this reveals that the automation regime for the tests is not yet mature.
Which of the following statements is TRUE?
- A. The test process should be radically changed to gain additional benefits from using the tool.
- B. The pilot project should have been critical so that maximum benefits were delivered
- C. The approach used for deployed this tool is aligned to the standard success factor for deployment
- D. The target defined for the project was inappropriate, because the automation regime for the automated tests at the end of the pilot is not yet mature.
Answer: C
Explanation:
The statement reflects the standard success factors for deploying an automation tool, which include rolling out the tool incrementally and adapting processes to fit with the use of the tool1. This approach allows for a controlled and measured implementation that can be adjusted based on feedback from each phase of the rollout. It is common for the test automation regime to not be fully mature immediately following a pilot; maturity develops over time as the tool is integrated into more projects and processes are refined.
References = The answer is based on the ISTQB Advanced Level Test Automation Engineer syllabus and the recognized best practices for deploying test automation tools as outlined in ISTQB materials21.
NEW QUESTION # 56
Which of the following describes how a test execution report is likely to be used?
- A. To understand which test step caused the failure in a test case
- B. To identify problematic areas of the SUT by keeping a history showing which test cases fail the most
- C. To measure coverage of the test basis by a test suite
- D. To record how a test case failure has been fixed
Answer: B
NEW QUESTION # 57
Which of the following attributes should NOT be included in a test execution report associated with a suite of automated tests?
- A. Environment in which the tests have been executed
- B. System/Application under test and its version
- C. Defect clusters identified during test execution
- D. Summary of the test execution results
Answer: C
NEW QUESTION # 58
......
ISTQB CT-TAE certification is particularly valuable for professionals who work in software development and testing. It provides them with the skills and knowledge needed to design, implement, and execute automated test cases effectively. Certified Tester Test Automation Engineer certification helps testers to improve their efficiency, reduce testing time, and deliver high-quality software products.
In addition to helping individuals advance their careers, the CT-TAE certification also benefits organizations that employ certified individuals. By having certified test automation engineers on staff, organizations can ensure that their automated testing efforts are effective, efficient, and of high quality, which can ultimately lead to cost savings and improved product quality.
ISTQB CT-TAE Official Cert Guide PDF: https://www.dumpstests.com/CT-TAE-latest-test-dumps.html
Exam CT-TAE: Certified Tester Test Automation Engineer - DumpsTests: https://drive.google.com/open?id=1Y5vdQ_d7pWkmY7hGxk2EyoT35lK5TvWf